Description

It's important for energy project developers to engage local communities in order to address any local concerns and adverse impacts that may arise from new infrastructure projects.  This training highlights how community engagement may be addressed in the permitting reform process, and key messages for congressional offices.

Select a tab below to read, watch, listen, or explore resources related to this training.

  In This Training
  1. What Is Community Engagement?
  2. Why Engagement Matters and What Goes Wrong Without It
  3. When Endpoints Are Unclear
  4. Growing Community Opposition
  5. The Relationship Between Engagement and NEPA
  6. Striking the Right Balance
  7. Policy Proposals to Improve Engagement
  8. Key Messages on Community Engagement
  9. Summary

What Is Community Engagement?

Community engagement is the process of early, ongoing communication between project developers, government agencies, and local communities. When done well, it allows all parties to share information transparently, understand local concerns and priorities, identify opportunities for mutual benefit, and improve project design. In some cases, meaningful engagement may even lead developers to reconsider a project entirely if community needs cannot be met.
The goal of community engagement isn't just to check a box — it's to create a trusted environment where decisions can be made with clarity, confidence, and community support. It is not simply a step in the permitting process. It's a foundation for everything that comes after.
Key Insight: Community engagement done right doesn't slow permitting down — it speeds it up. Projects that invest in early, meaningful engagement with local communities face fewer surprises, less litigation, and faster final decisions. Early investment in trust pays off in the back half of every project timeline.


Why Engagement Matters and What Goes Wrong Without It

When Engagement Works
Genuine community engagement creates a stronger foundation for every stage of a project. It results in:

  • Better project planning — local knowledge surfaces real concerns that developers may not have anticipated, allowing for adjustments before they become expensive problems
  • Community buy-in — when communities feel heard and see their input reflected in project design, they are far more likely to support the project moving forward
  • Timely, durable decisions — regulators can move with greater confidence when they know community concerns have been addressed, not just noted
  • Prevention of harmful projects — engagement ensures that projects with unacceptable impacts on communities can be identified and either redesigned or rejected before significant resources are wasted

When Engagement Fails
When project developers skip early engagement or treat it as a formality, the consequences are predictable and costly:

  • Communities feel blindsided — distrust grows rapidly when the first time residents hear about a major project is when it's already permitted or under construction
  • Misinformation fills the gap — in the absence of transparent communication from developers, rumors and worst-case narratives spread through communities and social media
  • Projects face delays, lawsuits, or cancellation — opposition that could have been addressed early becomes entrenched, leading to expensive litigation and, in some cases, project collapse
  • Negative sentiment can translate into bans — in some communities, poorly managed projects have triggered local ordinances banning entire categories of energy technology, creating lasting barriers to future development

Growing Community Opposition

Community engagement problems aren't only about too little engagement — they're also about engagement without structure. When there are no clear decision points or firm timelines, a different set of problems emerges:

  • Projects get stuck in prolonged uncertainty, unable to move forward even when engagement has been substantive
  • Repeated rounds of engagement without resolution erode community trust rather than building it
  • Delays increase costs and slow the deployment of needed infrastructure
  • Lack of decision clarity tends to generate more conflict, not less — because no one can tell when the process is actually finished

Key Insight: The problem isn't just insufficient engagement — it's also engagement without endpoints. A good community engagement process takes input seriously, allows well-vetted projects to move forward, and gives communities confidence that their concerns will be heard and resolved.


Growing Community Opposition

Community opposition to energy infrastructure is not a fringe phenomenon — it is widespread, growing, and increasingly consequential for the clean energy transition. Research tracking local opposition to infrastructure projects has documented:

  • Over 500 solar projects facing organized local opposition
  • Over 270 data centers facing opposition
  • Over 250 wind farms facing opposition

Critically, this opposition is driven not just by the projects themselves, but by how and when communities are engaged. Many communities that might have accepted or even welcomed a project had they been involved early become firmly opposed after feeling ignored, deceived, or steamrolled.

For the clean energy transition, this matters enormously. Solar, wind, and transmission projects are exactly the infrastructure we need to build — and they are the projects facing the most community opposition right now. A permitting reform package that doesn't address community engagement is one that will continue to see projects delayed or derailed, regardless of how streamlined the regulatory process becomes.

Key Insight: Opposition is often not really about the technology — it's about the process. Communities that experience early, transparent, and respectful engagement are far more likely to support projects than those that feel excluded from decisions being made about their own backyards. Fixing engagement isn't just good policy — it's a practical strategy for getting clean energy built.


The Relationship Between Engagement and NEPA

The National Environmental Policy Act (NEPA) is the primary federal law governing environmental review of projects with a federal nexus. But NEPA actually says relatively little about community engagement. Federal regulations previously encouraged engagement practices, but many of those regulations have been rolled back.

One significant connection between NEPA and engagement: requiring comment submission in order to establish legal standing to sue would also effectively mandate that community members engage with the process early — because those who don't participate formally lose the ability to challenge projects in court. This creates a legal structure that incentivizes early engagement, even in the absence of explicit requirements.

Reversed Party Perspectives

Permitting and community engagement reveal an interesting reversal of typical partisan dynamics. Normally, Democrats are more inclined to trust federal agency expertise, while Republicans tend to be skeptical of government overreach and agency power. On permitting, these positions flip.

Allowing a permit to stand — and preventing its reversal through litigation or executive action — requires trusting that the permitting agency made the right call. Republicans tend to support this deference when it means getting projects built; Democrats are more likely to want to preserve the ability to challenge agency decisions through litigation or executive review.

Community engagement sits at the intersection of these tensions. Done right, robust early engagement can satisfy both priorities: it gives communities a meaningful voice (a Democratic priority) while creating a structured process that leads to clear, durable decisions rather than endless litigation (a Republican priority). The policy goal is to strike a balance that both parties can recognize as fair.


Striking the Right Balance

The central challenge in designing good community engagement policy is that engagement must be both strong and structured. A well-designed community engagement system:

  • Takes input seriously — communities must be able to meaningfully shape project outcomes, not just submit comments that disappear into a bureaucratic void
  • Improves or rejects bad projects — the process must have real teeth, with the ability to require design changes or halt projects that genuinely cannot meet community needs
  • Allows well-vetted projects to move forward — once a project has gone through rigorous engagement and addressed legitimate concerns, there must be a clear mechanism for moving forward without indefinite re-litigation of settled questions
  • Is time-bound — engagement must have clear start and end points, so communities know when their window to participate is open and developers know when they can expect a decision

"There was broad agreement that early and trusted community engagement is an effective tool in reducing permitting delays."Bipartisan Policy Center Expert Roundtable


Policy Proposals to Improve Engagement

A range of concrete policy proposals have emerged from bipartisan discussions on how to improve community engagement in the permitting process. These proposals share a common goal: making engagement earlier, more inclusive, more substantive, and more time-bound.

Community Benefits Agreements

One of the most direct tools for aligning project development with community interests is the Community Benefits Agreement (CBA) — a voluntary contract between a project developer and a coalition of community organizations. CBAs can include a wide range of locally tailored benefits:

  • Local hiring preferences and workforce development programs
  • Contributions to affordable housing in the surrounding area
  • Green spaces, parks, or environmental protections near the project site
  • Commitments to environmental monitoring and community notification

When done well, CBAs reduce community opposition by giving residents a direct stake in the project's success — transforming a project from something happening to a community into something the community has a hand in shaping.

Structural Engagement Reforms

Beyond CBAs, a set of structural reforms would improve how engagement works across all types of projects:

  • Independent third-party facilitators — Establish and fund non-biased third parties to perform community education and engagement on energy technologies. Independent facilitators are more trusted than project developers and can help communities understand what they're being asked to weigh in on
  • Project monitoring committees — Establish local stakeholder committees for individual projects that monitor compliance with engagement commitments throughout the project lifecycle, not just during permitting
  • Agency prioritization of early engagement — Direct federal agencies to prioritize early engagement and consensus building as a core part of their permitting function, not an afterthought
  • Community information hearings — Conduct and resource extensive community information sessions that allow residents to submit comments and receive substantive responses, not just form acknowledgments
  • Online engagement clearinghouse — Establish a centralized online platform where community members can find information about engagement opportunities for projects in their area, lowering the barrier to participation
  • Public participation advisory commissions — Establish expert commissions to advise agencies on the design, implementation, and evaluation of public participation processes, ensuring engagement practices are evidence-based and continuously improving
  • Clear timelines and decision points — Establish firm timelines for each stage of the engagement process, with clear decision points that allow well-vetted projects to move forward while ensuring engagement has been genuine

Key Messages on Community Engagement

Effective advocacy on community engagement can resonate across the political spectrum — but the framing matters. Here are the core messages, organized by audience.

Topline Messages for All Audiences

Message 1: Early, structured engagement reduces costly delays and litigation

Getting input early is more efficient than fixing problems after the fact. Clear timelines on when input is welcome help avoid endless delays and uncertainty. Strong community engagement leads to better projects and faster decisions. Predictable processes reduce conflict and litigation risk for everyone — developers, communities, and agencies alike.

Message 2: Permitting reform gives us the chance to ensure communities have a meaningful voice and decisions are made responsibly

These projects are happening — the question is whether communities will have a real say in how. Early engagement ensures projects reflect local needs and priorities. Clear decision points ensure accountability and follow-through from developers and agencies. Doing nothing keeps a system that fails both communities and clean energy progress.

For Republican Offices

Republicans are often skeptical of new mandates and process requirements. Lead with efficiency and predictability:

  • Reduce litigation risk — Early engagement gives communities a voice upfront, which dramatically reduces the odds of costly lawsuits after a project is permitted
  • Faster decisions — Structured engagement with clear endpoints means projects don't get stuck in open-ended review. Everyone benefits from knowing when the process is finished
  • Local control — Community engagement empowers local stakeholders — not distant bureaucrats — to shape decisions about infrastructure in their own backyards
  • Better outcomes for less money — Projects that invest in early engagement cost less in the long run by avoiding the delays and redesigns that come from discovering community concerns too late

Avoid: Framing community engagement primarily as a mandate or regulatory requirement. For Republican offices, emphasize voluntary tools like Community Benefits Agreements and the efficiency gains of getting engagement right early.

For Democratic Offices

Democrats care deeply about environmental justice, community voice, and ensuring that the clean energy transition doesn't repeat the harms of past infrastructure development. Lead with equity and accountability:

  • Meaningful community voice — These projects are happening — the question is whether frontline and disadvantaged communities will have a real say in how they are designed and where they are sited
  • Environmental justice — Good engagement processes ensure that communities that have historically borne the greatest burdens of energy development are centered in decisions, not sidelined
  • Accountability — Clear decision points and monitoring committees ensure that developer commitments to communities are followed through, not made and forgotten
  • Doing nothing fails communities — The status quo — with inadequate engagement requirements and no clear endpoints — is already failing the communities we care about. Reform is an opportunity to get this right

Avoid: Framing community engagement as primarily a tool to slow or stop projects. For Democratic offices, the goal is to ensure communities have a real voice in well-designed projects — not to create new veto points that prevent needed clean energy infrastructure from being built.


Summary

All recordings from the Permitting Reform training series are available at community.citizensclimate.org/topics/clean-energy-permitting-reform 

Video Outline

Skip ahead to the following section(s):

  • (0:00) Intro & Agenda (0:00)
  • (1:48) Community Engagement Background
  • (12:50) Recognition of its Importance
  • (14:18) Engagement Policy Proposals
  • (19:01) Key Messages

Instructor(s)
  • Jenn Tyler
  • Dana Nuccitelli

Downloads

View/download Google Slides

Download Video

Community Engagement and Key Messages
Audio Outline

Skip ahead to the following section(s):

  • (0:00) Intro & Agenda (0:00)
  • (1:48) Community Engagement Background
  • (12:50) Recognition of its Importance
  • (14:18) Engagement Policy Proposals
  • (19:01) Key Messages

Instructor(s)
  • Jenn Tyler
  • Dana Nuccitelli

Downloads

Download the podcast

Listen to the training
Training Resources

Have you completed this training?

Let us know if you've completed this training! Your progress will be logged in the Action Tracker so you can reference a list of trainings that you've completed.

Log your training


Discussion Topic

Share your experience or ask questions related to this training in the forums.

Join more discussion on CCL's Nerd Corner


To Print

Instructions for printing this page on CCL Community.